Fencing repairs and the associated prior clearance work continued on the Alton section, and on Tuesday, sand, cement, bricks, drums of water, and concrete flooring units (troughing lids) were delivered along with the sleepers removed from Alresford to the A31 embankment, to allow the Saturday gang to continue with the construction of the new Pway hut.
Many thanks are extended to Bernie, the mid-week gang, and the Engineer's train, without whom these materials would have had to be transported the hard way!