With the gang re-assembled at M&FM, they received a report of a broken section of fence down the line at Wanders Curve on the Ropley section. Keith and Martin gathered together fencing materials and left to investigate, with Eddie and Tony to join them after they had dropped off tools and materials at Chawton with the Company transport, to allow Neil, Matt, Paul, and Adrian to continue with the construction of the Chawton Heights hut.
The reported broken fence turned out to be a loose top wire, which was duly re-tensioned, the lower wires all being intact albeit a little rusty (the source of the report clearly needs to go to Specsavers!-Ed). A couple of holes were found however between Grosvenor Road bridge and Wanders farm crossing, which were re-wired.
The hut construction team managed to trim the edges of the roof sleepers at the rear in readiness for felting (on Monday), excavated and cast a short section of foundation for a course of brickwork to be laid below the door threshold, cut and fitted infill timbers above the door frame, and started to excavate the ground inside the hut down to formation level for the laying of the concrete floor slabs.
| Neil, Paul, and new gang member Matt reduce the ground levels in front of the door and excavate the foundation trench for the single course of bricks to be laid below the door threshold |
| Neil casts the foundation |
![]() |
| The ground level inside is reduced in readiness for the laying of the concrete floor slabs. Infill timbers fitted above the door. |