| Neil and Paul return from the completion of their line inspection at Alresford head shunt back to the Station for much needed refreshments |
The other team, by now reduced to three (Ian J, Neil, and Adrian), went down to the Chawton Heights Pway Hut site, where Ian and Neil proceeded to lay and fix the plywood sheeting on the roof, and Adrian set about completing the timber boarded infill panel in the wall behind the chimney. After taking lunch, they were joined by Martin R, who brought with him further refreshments in the form of a flask of tea and box of mini blueberry muffins (good man). Their final task of the afternoon was to fit the door frame, before being re-united again with RNB team back at base, who had surprisingly completed the maintenance task on the whole section of flat bottom track (they say that one volunteer is as good as ten pressed men, which is certainly the case here!)
![]() |
| Ian trims the edge of the plywood sheeting laid on the Pway hut roof |
![]() |
| Adrian completing the timber boarded infill panel, fitted in the wall behind the chimney |
| The frame in place. An infill panel of short lengths of timber is to be fitted above |
| The cover battens and fascia boards in place. The shorter third and fourth battens from the left are to allow for the huts name plaque, currently being manufactured by Neil |